VEC Oman – Tie-In Works – Farah Expansion and Saiwan Expansion

Project Summary:

  • Block 3 & 4 Development Project Phase 1for Farah expansion at Oman

Scope: Pre-Bid Engineering of Gas Compression Facilities for phase 1-Tie in works, Piping Stress Analysis, GA, ISO & MTO Generation, Complete Basic & Detailed Engineering of Gas Compression Facilities.

 

Tridiagonal Solutions Ltd. – High Pressure Erosion Test Facility

Project Summary:

  • 100 Bar, 50 CFM compressors
  • High Pressure Sand Injection System
  • Liquid Nitrogen System

Scope: Feed and Conceptual Studies, Complete Basic & Detailed Engineering.

 

Atlas Copco – Nitrogen PSA Generator Package

Project Summary:

  • Modular vessel skid

Scope:Skid Design using STAAD, Transportation Analysis, Inplace Analysis & Lifting Analysis.

 

HPCL – Diesel Hydrotreater Plant, VIZAG

Project Summary:

  • Diesel hydrotreater plant

Scope:4.5Km long pipe rack design, GA, ISO & BOM preparation, Piping Stress Analysis, Pipe rack & flare trestle design, Design & detailing of foundations.

 

Gujarat Gas Limited (GGL) – Underground Pipeline Analysis

Project Summary:

  • Underground buried natural gas pipeline (size range 4” to 12”) from Kutch to Jamnagar

Scope: Pipe stresses generated due to seismic loads checked against allowable stress for steel pipe, Analysis using STAAD pro software.

 

Sabarmati Gas Limited (SGL) – Underground Pipeline Analysis

Project Summary:

  • Road widening affects underground buried natural gas Pipeline

Scope: Engineering consultancy services for pipeline protections & recommendations, Stress analysis for static as well as dynamic load calculations, API/ASME calculations & Seismic analysis.

 

Reliance Industries Limited (RIL) – Twin Pipeline Re-Routing

Project Summary:

  • JNPT to Kalamboli and Mahul to Patalganga twin pipeline of 8”dia.

Scope: Basic and detail engineering rerouting of pipelines, Validation of existing documents and drawings & Construction scope of work

 

Worley Parson – Seismic Fault Crossing Design – HPCL / VDPL

Project Summary:

  • 16” Dia Product Pipeline
  • Total 711 Km Length
  • 26 no. of Faults

Scope: Seismic Fault Crossing Design

 

Mineral Technologies Ltd. (Downer Group) – Wet Mineral Processing Plant

Project Summary:

  • Mineral Processing Plant in Bangladesh consisting of wet and dry mineral processing stages
  • Designed to process 8 t/h of mineral sands

Scope: Design and Engineering of Plant, 3D Modelling, MSRQ, Data Sheets for Procurement of Packages, Piping/Electrical/Civil Engineering & Construction Support.

 

Kalpataru Power Transmission Ltd. – Mehsana-Bathinda Pipeline (Sections IV & V) of GIGL

Project Summary:

  • MBPL Section-IV: 1 IP-Station&4 SV-Stations, 134 Km long Pipeline of 30” Dia
  • MBPL Section-V: 1 IP-Station, 3 DT/RT & 5 SV-Stations, 180 Km long Pipeline of 30” Dia

Scope: Detail Engineering

 

Corrtech International Pvt Ltd. – Mehsana-Bathinda Pipeline (Section VI) of GIGL

Project Summary:

  • MBPL Section-VI: 1 IP-Station&3 SV-Stations, 134 Km long Pipeline of 18” Dia

Scope: Detail Engineering

 

Harji Engineering Pvt Ltd. – Pumping Station at IOCL Paradip & Balasore

Project Summary:

  • Pumping Station

Scope: Piping Stress Analysis of Pump Station, Preparation of Piping Isometrics& Preparation of Pipe Support Drawings

 

Green Dome Petrochemicals – Laser Scanning and 3D Modelling Ammonia Plant

Project Summary:

  • 1180 MTPD Ammonia Plant in Ajman, UAE

Scope: Complete Plant Scanning of Plot Area 63,638 sq. meters– using FARO Focus 3D Laser Scanner, Conversion of Scanned Images into 3D Model